For Suppliers and Partners 
project opportunities

Project Opportunities
Capital projects included in RG&E’s 2018 Capital Investment Plan (CIP) Filing that passed the NWA Screening Criteria are included below:

Transmission/
Distribution

Project Name

 Time of Need

 Estimated RFP Release Timing

Distribution

Station 156 transformer/facilities upgrade

2022

2018

Distribution

Station 51 transformer/facilities upgrade and secondary source addition

2022

2018

Transmission

Station 121 - Add 115-34.5 kV Transformer

2022

2018

Distribution

Station 127 (replace bank 1 and convert to 12 kV)

2023

TBD

Distribution

New 115-12.5 kV Station on Manitou Road

2024

TBD

Transmission

Station 204 - Add 115-35 kV Transformer

2024

TBD

Distribution

Station 46 - Replace #1 and #3 Transformer Banks

2025

TBD

Transmission

Add New 35 kV Circuit - Offload Circuit 778

2025

TBD

Transmission

Station 158 - Replace Two 115/34.5 kV Transformers

2025 

TBD

Distribution

Station 192 transformer/facilities upgrade

2026

TBD

Transmission

Add 35 kV Circuit (S42 - S420 - S62 - S85), Offload Circuit 780

2026

TBD

Transmission

Add 35 kV Circuit (S80 - S110 - S106), Offload Circuit 765

2026

TBD

Transmission

Upgrade 35 kV Circuit 726 (Station 42 - Station 43)

2026

TBD

Distribution

Station 117 - Replace #1 Tranformer Bank and convert 3 circuits to 12 kV operation

2030

TBD

Upcoming Projects

Station 51
Station 51 Substation, located north of Rochester in our distribution area, is a reliability improvement project.  The station provides service to customers with significant loading.   If the station transformer were lost the areas distribution system would not be able to support the load during the summer peak period. This project will increase station capacity and develop a second source contingency. The traditional wires project is to replace the existing 11-4.16 kV, 6.25 MVA station transformer with a new 11-4.16x12.47 kV, 14 MVA LTC transformer. The scope of work is to extend a new 34.5 kV line 773 to Station 51 and establish a new 34.5 kV transmission source feeding a second 34.5-4.16x12.47 kV, 14 MVA LTC station transformer. We plan to release an RFP for NWA solutions in 2018.

Station 156
Station 156 Substation, located in Manchester, Ontario County is a load relief and reliability project. The station provides service to customers with significant loading. The traditional wires project is to replace the two (2) existing 34.5-4.16 kV station transformers with two (2) new 34.5-12.47 kV, 14 MVA LTC transformers and convert all three (3) 4.16 kV circuits to 12.47 kV operation. We plan to release an RFP requesting NWA solutions for this project in 2018..

Station 121
Station 121 Substation is located in Macedon, Wayne County. The traditional wires project is to install a second 115/34.5 kV, 30/40/50/56 MVA, LTC transformer at Station 121 that will allow adequate voltages and thermal conditions to be maintained in the area for an outage of the existing 115/34.5 kV transformer at the substation. We plan to release an RFP requesting NWA solutions for this project in 2018.